Thursday, 16 October 2008

Happy from Northampton

Our Architect called me at work on Wednesday to say that 'he was on site and he was very happy'. A good sign i thought because as interesting as piles are to the untrained eye the verification that they were good from a professional is good to here.

Over the last few days the newly installed piles have been cut down to uniform height and are now being interlinked with steel beams. That Ladies and Gents is the biggest bit done we can lay the concrete and build the steel structure.

The bricks are ordered and should be on site in 6 weeks by which time the frame should be ready to be built around.