So near and yet so far




Its frustrating at the minute because I cant see the sort of progress taking place that Ive been used to whilst driving past on the way to and from work. So I ditched the car this evening and walked around the perimeter of the building to try and ascertain what progress has been made since Sunday's visit. Here's whats changed :

  • The door frames have now been fitted internally
  • All the main hall is now painted
  • More flagging has appeared on the car park
  • A vent hole has appeared in the oak street elevation where the kitchen is
  • Two wires are protruding from the oak street elevation one either side of the door presumably for security lighting to be fitted
  • The missing pane of glass in the Oak Street Side Entrance is now in place
  • Additional down spouts for the guttering are in place
So all in all quite a bit. Still to do however

  • Finish Paving and tarmac the carpark
  • Fit the suspended ceiling in the main hall
  • Hook up all the electrics
  • Fit Ceiling tiles
  • Fit Lights
  • Hang all internal doors
  • Make and fit the kitchen serving hatch
  • Clear and clean the site
  • Test fire alarms
And all of this is scheduled to be completed with the ext 7 days. Next Thursday is likely to be what is known as a handover meeting.......we hope !

CB