Its frustrating at the minute because I cant see the sort of progress taking place that Ive been used to whilst driving past on the way to and from work. So I ditched the car this evening and walked around the perimeter of the building to try and ascertain what progress has been made since Sunday's visit. Here's whats changed :
- The door frames have now been fitted internally
- All the main hall is now painted
- More flagging has appeared on the car park
- A vent hole has appeared in the oak street elevation where the kitchen is
- Two wires are protruding from the oak street elevation one either side of the door presumably for security lighting to be fitted
- The missing pane of glass in the Oak Street Side Entrance is now in place
- Additional down spouts for the guttering are in place
- Finish Paving and tarmac the carpark
- Fit the suspended ceiling in the main hall
- Hook up all the electrics
- Fit Ceiling tiles
- Fit Lights
- Hang all internal doors
- Make and fit the kitchen serving hatch
- Clear and clean the site
- Test fire alarms
CB