Tuesday, 2 December 2008

'You should have put the lid on first !'


'Snow in winter who would have imagined' said Duncan our site foreman when I went to see him this morning.


Work continues in spite of the snow, our remaining reinforced concrete floor slabs are being put in situ today. Once this is completed, the baptistery will be constructed in the corner of the main worship area. The roofer is lined up to start shortly and the stone should soon be arriving so that the walls can go up.


Duncan reports that the build is progressing well and there are no issues for us to address. All good stuff.